The construction along East Green Bay Street has begun.
Location: Between County B and Zingler Street & Main Street and County BE
Schedule: July 15, 2019 to November 1, 2019
Traffic impacts:
- Single lane closures and 10-foot lane widths on WIS 22 between County HHH/Airport Road and County BE will continue through September.
- Single lane closures on WIS 22 between Main Street and Eberlein Park will continue.
- Shoulder closures on Main Street between County B and Zingler Avenue will be intermittent over the next few weeks to complete curb and sidewalk repairs.
- On Saturday August 3, WIS 22 (Green Bay Street) will close at the railroad crossing between Hamlin Street and Ellis Street. A signed detour will be in place utilizing Main Street to WIS 29 to Airport Road. No access across the railroad will be allowed as it will be under construction. Access to businesses and residents within the closure limits will be maintained. Work along WIS 22 (Green Bay Street) outside the road closure limits will continue with lane closures, access to businesses and residents will be maintained.
Anticipated work scheduled for next week, crews will:
- Continue work on the new box culvert at Murray Creek.
- Continue replacing curb ramps on Green Bay Street (WIS 22), westbound
- Begin removals and installation of new curb ramps on Main Street between County B and Zingler Avenue
- Begin reconstruction of Green Bay Street at the Railroad Crossing between Hamlin Street and Ellis Street, starting on August 3, 2019
Website: https://projects.511wi.gov/wis22resurf/
Please view the image below for information regarding detour routes to avoid this construction area.
If you have any questions, please feel free to contact the Public Works Department at 715-526-3512.