photo credit Wisconsin DOT
Resurfacing of WIS 22 from County B to Zingler Road, Main Street to County BE
Project Overview
The project is a resurfacing type project programmed in order to improve the existing pavement driving surface and other deteriorated infrastructure. The existing asphaltic pavement is showing signs of deterioration with transverse and longitudinal cracking throughout. If no improvements are completed, the remaining pavement structure life will be significantly reduced. Other needs that are also present along the project include:
- The existing box culvert at Murray Creek is deteriorating and in need of replacement and the guardrail does not meet current safety standards for crashworthiness.
- The curb ramps do not meet ADA standards.
- The existing railroad crossing surface is deteriorating and does not meet profile geometric standards through the crossing.
- There are signals but no gates present at the crossing.
Most of the work will be improving sidewalk curb ramps, resurfacing the existing pavement, and replacing the box culvert at Murray Creek just east of Rusch Road. Crews will also replace the railroad crossing on WIS 22 in downtown Shawano. Work consists of grading, base, milling, asphalt pavement, culvert pipe, storm sewer, curb and gutter, concrete driveway, sidewalk, box culvert replacement, signs, and pavement markings.
At the completion of the project, sidewalk curb ramps will be improved and up to current standards.
Traffic Impacts as of July 24, 2019:
- Single lane closures and 10’ lane widths on WIS 22 between County HHH/Airport Road and County BE will continue through September.
- Single lane closures on WIS 22 between Main Street and Eberlein Park will continue.
- On Saturday August 3rd, WIS 22 (Green Bay Street) will close at the Railroad crossing between Hamlin Street and Ellis Street. A signed detour will be in place utilizing Main Street to WIS 29 to Airport Road. No access across the railroad will be allowed as it will be under construction. Access to businesses and residents within the closure limits will be maintained. Work along WIS 22 (Green Bay Street) outside the road closure limits will continue with lane closures, access to businesses and residents will be maintained.
Anticipated work scheduled for week of July 29, 2019:
- Finish building the temporary diversion channel
- Begin demolition of the north half of the existing Murray Creek Box Culvert
- Continue replacing curb ramps on East Green Bay Street (WIS 22), eastbound
- Begin construction of the north half of the new Murray Creek Box Culvert
Meeting information:
Our next public informational meeting will take place Monday, July 29 at 3 p.m. at City hall in the River Room. A brief update will be given on the status of the project as well as describe in depth the schedule and traffic impacts for the closure of Green Bay Street at the Railroad. This road closure will begin on Saturday morning 8/3/19. A signed detour will be in place utilizing Main Street to WIS 29 to Airport Road. Local traffic will utilize East 5th Street as an alternate route around the road closure.